S.No | Name of work | Contract value (Rs. in Crores) | Expected Date of Completion | ||
ACV in Crores | Out Standing Value | % of Completed | |||
1 | "Two laning of existing hunli-anini road on epc basis from design km 53.500 to km92.500 (existing km 56.320 to km 97.650) package-ii in the state of arunachal pradesh under sardp-ne" (epc) mode. | 434.06 | 199.58 | 54.02% | Feb-2021 |
HUNLI - ANINI ROAD FROM KM.53.500 TO KM.92.500 NH-313 |
![]() |
![]() |
![]() |
![]() |
COMPACTION & GRADING |
![]() |
![]() |
![]() |
EARTH WORK EXCAVATION |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |